Office of Rail Regulation

0

Network Rail's delivery in CP5


keywords: click to search
Office of Rail Regulation
ORR
maintenance
renewals



Phrases in [single square brackets] are hyperlinks in the original document

Phrases in [[double square brackets]] are editorial additions or corrections

Phrases in [[[triple square brackets]]] indicate embedded images or graphics in the original document. (These are not usually archived unless they contain significant additional information.)


Office of Rail Regulation

Network Rail's delivery in CP5
_______________________________________________________________


date
9 December 2014
source Office of Rail Regulation
type Letter



OFFICE OF RAIL REGULATION

Richard Price
Chief Executive

Mark Carne
Chief Executive
Network Rail
1 Eversholt Street
London NW1 2DN

9 December 2014


Dear Mark

NETWORK RAIL'S DELIVERY IN CP5

We met on 18 November to take stock of Network Rail's performance against the regulatory outputs for the first six months of CP5. We also discussed some of these issues when our Boards met recently, and you and I had a further discussion on this last week.

Overall, the first six months of the control period have proved very disappointing, even against the revised performance plan agreed after for the first two years of CP5. You have acknowledged this. This letter sets out our key points of concern. There are areas in which we need to see focussed action to improve your planning and delivery in CP5 so that the railway's customers and taxpayers get the service and improvements they are paying for.

Performance
It is clear that train performance is not where it should be against the revised plan, whether using the public performance measure (PPM) or on cancellations and significant lateness (CaSL). It is also clear from the data that the causal factors vary across Network Rail's ten routes, but a common feature is higher-than-expected rates of asset breakdowns. Although the overall number of infrastructure asset failures has declined (measured by your composite reliability index), it remains higher than the level that Network Rail indicated was needed to underpin the recovery in service reliability and punctuality committed to in the agreed CP5 delivery plan and the subsequent performance plan.

You pointed to 'reactionary delay' as the largest single contributor to the worsening PPM (ie: a growing impact of knock-on delays, whatever the initial problem, reflecting things like more congestion on the network). We recognise that franchised passenger journeys have risen by 4.4% in quarter 2 of 2014-1S compared with the same period

a year earlier, and that this presents challenges on a congested network. We understand that the further decline in performance since CP4 contains an increase in reactionary delay, however reactionary delay is a multiplier on primary delay, and is therefore a function of where and when the delay occurs, not just the ability of the train operators to recover.

The impacts on passengers of long delays can be more serious than the S-and 1 aminute thresholds in the PPM statistics imply. We are therefore particularly concerned by year-end forecasts for CaSL for a number of operators which show that their outturn position is likely to be worse than the threshold of 0.2percentage points below the individual TOC Performance Strategy we specified in the Final Determination as the point at which we would investigate. We are keen therefore to see the outcome of your 02 Performance Strategy reviews with each of the TOCs and the updates these will require to your plan.

As we discussed, I want to be assured that Network Rail is meeting its commitments on the things which are substantially under your control -notably the condition, reliability and operation of the network. We are under no illusions that the solutions to poor punctuality require cooperation across the whole industry, but it is incumbent on Network Rail to meet its commitments on asset condition and reliability. We need to see harder evidence that you are putting in place effective plans which will achieve this -and this leads on to our observations on renewals and maintenance.

Renewals and maintenance

Though performance of the network is a complex issue, improving the condition and reliability of your assets is at the heart of your role in managing risks to service reliability and punctuality across the network. As noted above, asset reliability is improving but not at the rate needed to sustain improved service reliability, and for which you were funded to deliver.

You have proposed a five-point whole-industry strategy for addressing performance, and this is welcome. However as we discussed, three of the five points -- increased asset reliability, 'eliminating' temporary speed restrictions (without compromising safety) and improved weather resilience -- are wholly or very largely dependent on the integrity and delivery of your maintenance and renewals plans; and a fourth reactionary delay-is a function of primary delay, which is also dependent on asset reliability. That is why we are so concerned about Network Rail's under-delivery of key volumes, the lack of clarity that work is being done at the critical points in the network which make the biggest difference for customers, and indeed whether the data you use to plan and monitor progress is adequate for the task.

At the end of CP4, Network Rail's performance on punctuality and service reliability was below target, and worse than the company had projected in its strategic business plan (SBP) for CP5. You proposed in January to revise the CP5 England and Wales year 1 performance trajectory downward from 91.9% to 91.1% for 2014-15. We agreed not to hold NR to account to the regulatory targets in years 1 and 2..

Instead we said that we would focus on the delivery of your plans to restore performance to the committed level during CP5-taking into account delivery of your performance plan as well as your maintenance and renewal plans as evidence that you are doing everything reasonably practicable to give passengers the levels of service to which you committed. It is with this in mind that we express our concerns below on your maintenance and renewal delivery.

Renewals

Reflecting the problems with delivery in CP4, we are monitoring a range of inputs in CP5 in addition to the regulated outputs. Having scrutinised the data, we raised our concerns around renewals volume reporting in my letter of 30 October on data quality. Among other things we were surprised to see large fluctuations both up and down in the cumulative volumes.

Network Rail's SBP submitted to the ORR in January 2013 was route based.

Therefore we met with every route managing director at the start of 2014 to challenge them on issues such as:
•
whether they owned and were committed to implementing the SBP
(particularly in the first 2 years)
•
whether they had the network access to deliver the SBP
•
whether the supply chain contracts and Network Rail resources were in place and scheduled to deliver the SBP.

All routes confirmed that they owned the plan, were committed to the plan and could deliver it. When the revised plan (delivery plan) was finalised early this year there were some significant differences from the SBP which your team were able to explain and again give us assurance that you could deliver your new plan.

However, after seven periods, there are major discrepancies between the volumes in the delivery plan and what has been delivered in practice, across all asset groups. The commentary on volumes in your Period 8 Finance Pack shows that so far this year you have delivered the following percentages of your delivery plan:

Asset category
% of renewals plan delivered by 2014-15 Period 8
Track Plain Line
90%
Track Switch and Crossing (S&C)
51%
Signalling
53%
Civils -Underbridges
45%
Civils -Earthworks
39%
Overhead line Equipment (OLE)
80%
Conductor Rail
44%

Renewing the assets is a very large part of your core role as the manager and operator of the railway infrastructure, and the credibility of your plans is key to demonstrating whether you are likely to deliver the commitments in the Final Determination. We therefore need your assurance that your recast plans are credible across all routes, based on a robust assessment of what is possible and how it will be achieved. You are undertaking a 'deep dive' on renewals and I would like to understand what you have concluded from that and the improvement plan you propose, including how you plan to ensure that your management information and local delivery planning is coherent and robust.

Maintenance

We also expressed real concerns around maintenance volume reporting where, on the basis of what you have reported; we cannot distinguish between deviations from your planned volumes and inaccuracies in your data. It is fundamental to any company to understand what it is buying for the money it spends. To ensure both effective delivery and to demonstrate efficiency it is imperative that the industry is able to clearly back up its expenditure and delivery projections with robust data. It is impossible to truly demonstrate the progress you have made in terms of financial efficiency without being able to track unit rates. If you cannot rely on your volume data then the unit rates become invalid.

I know you personally share these concerns. We consider that you need this information as a business in order to make informed asset management decisions and I am therefore pleased to see your commitment to improving this area in your letter of 3 December. I would be grateful if you could confirm when we will be able to see a comprehensive plan with dates and milestones that can be tracked in order to progress this issue once and for all.

Enhancements

Our Monitor reports on a number of milestones not being met in the first six months of CP5. I recognise that we are still at an early stage in CP5, but as we have discussed, slippage on critical milestones jeopardises the delivery and timing of important benefits to passengers and freight customers, including extra capacity to reduce crowding, and improvements to service reliability and journey times. We will continue to monitor these projects closely and will continue to seek clarity on how you are managing delivery risks. Our trilateral discussions with the OfT are helping to make sure the impacts of these risks on passengers are well understood, and we expect you to manage these so that inconvenience to rail users and deferral of benefits is minimised.

Your Enhancement Cost Adjustment Mechanism (ECAM) submissions are not as accurate as would be expected. For example the most recent East Coast submission contained a 40 per cent error in employer costs and omitted Schedule 4 costs for a particular activity.

We understand that you are changing your internal governance to address our concerns, which you share, on the cost escalation and missed delivery milestones for the enhancement portfolio. We agreed that you would come and present these new arrangements to our senior team shortly.

Conclusion

Though we are still at an early stage in CP5, the data do not yet show that the planned recovery in service reliability and punctuality for customers is happening, and that there are significant gaps in the work Network Rail had planned to underpin this recovery.

Specifically we will need to see:
•
the outcome of the 02 Performance Strategy reviews with each of the TOCs and the implications for changes required to your plan;
•
evidence that you are putting in place effective plans to achieve your commitments on asset condition and reliability and clarity on how you will recover and prioritise your plans for delivery of key maintenance and renewal volumes;
•
assurance that any recast plans are credible across all routes, based on a robust assessment of what is possible and how it will be achieved;
•
improvements in data quality for monitoring progress of delivery through a comprehensive plan with dates and milestones that can be tracked; and
•
your revised internal governance arrangements to show how you are addressing cost escalation and missed delivery milestones for network enhancements.

It is essential for your company's credibility as an infrastructure manager that this is put right. I know you share many of these concerns and I believe that, with your sustained focus on strengthening the organisation and improving delivery, Network Rail is capable of addressing them. It is essential that these issues are resolved quickly, and that rail users see the improvements to the standard of service they expect and have paid for.

Yours sincerely

Richard

RICHARD PRICE